CURRENT · WEEK 1
16 November 2026
Recorded work, corrected progress measures, and updated risks and cost performance.
View latest checkpoint ↓MYT Governance Lab · Portfolio Control Tower
— of — projects have forecast finishes later than their original Baseline 1 commitments. The largest slip is — (—), the priced projects are earning — of planned work (SPI), and each dollar spent buys — dollars of planned work (CPI).
Interactive checkpoint · Week 1 · In development. Explore the 16 November 2026 export from MYT’s Portfolio Control Tower lab, the first checkpoint with a week of recorded work. This page uses embedded simulated data and does not refresh automatically. Earlier history is reconstructed; MYT publishes reviewed updates manually at meaningful stages, typically every two to three weeks depending on program progress. This lab remains in development.
Follow the lab over time. Each checkpoint preserves the simulated data and decisions available on its date.
CURRENT · WEEK 1
Recorded work, corrected progress measures, and updated risks and cost performance.
View latest checkpoint ↓ARCHIVED
The earlier program position, with original and revised baselines, risks, and recovery decisions.
View previous snapshot →Reviewed updates are published manually at meaningful stages. This lab remains in development.
A PMO lead inherits four at-risk projects and has to decide, with data, what to do first. Each Monday a scheduled flow records a snapshot of every plan; everything before Nov 2 is reconstructed history.
Takeover. All four projects are Red. Regional is five weeks past its Baseline 1 finish with 11 tasks overdue, all traced to one stalled task: vendor master data that failed validation in August.
Decision CR-001. The delay is priced three ways before choosing a fix. The sponsor approves re-baselining Regional with containment (keep legacy invoicing live) over crashing or doing nothing. Baseline 1 is kept as the original commitment; Baseline 2 becomes the working plan.
The watermelon. The first automatic snapshot turns Regional Green: the re-plan moved its overdue tasks into the future, yet it is already behind its new baseline. Green outside, red inside. The health rule is changed the same day to weigh progress and record a reason.
Two CPIs. Actual costs are added, with an opening balance inherited from the finance ledger. Cumulative CPI keeps the inherited overrun visible; CPI since takeover will show whether it is still happening.
First team update. A fortnight of recorded work is approved and applied. Site A Gate 1 passes conditionally (approval came in late Friday, recorded Saturday). Typed-in progress on Sites A and B is corrected to match logged hours, and two unplanned invoices push CPI since takeover to 0.90. Lesson: Planner’s completed-hours figure follows each task’s schedule, not its percent complete, so earned value is now measured as percent complete × budget.
Week 1 snapshot. Health now records its reason. Regional is Green for a real reason this time: two points behind Baseline 2, inside tolerance, nothing overdue. Sites A, B and C stay Red, each with its slip and gap on record.
Nov 18: Regional’s vendor resubmission. Nov 27: Site A Gate 1 conditions due. Dec 4: Regional’s finance task due under Baseline 2.
Weeks between each project’s forecast finish and its original Baseline 1 finish, week by week. Drift is always measured against Baseline 1, so a re-baseline never hides slip. The dashed line is Regional’s approved Baseline 2: from the takeover on, holding at or below it is recovery.
Actual progress divided by planned progress against the baseline in force that week; 1.0 is on plan. A re-baseline restarts the plan, so Regional’s line breaks at the reset (ring) instead of jumping, which would look like a recovery that never happened.
Latest weekly snapshot. Health weighs slip, overdue critical tasks and, from Nov 16, progress against plan. SPI here compares percent complete; the cost table below weights the same work by dollars, so the two can differ. This week the snapshot’s actual percent for Sites A and B uses Planner’s completed hours, which understate the two corrected tasks (see the register).
| Project | Health | Planned | Actual | SPI | Why |
|---|
Baseline 1 is the accountability record. Where a change request approved a re-baseline, the current baseline is shown beside it.
| Project | Baseline 1 | Current baseline | Forecast | vs Baseline 1 |
|---|
Priced from a lab rate card (illustrative). Earned value is the budgeted cost of the work actually done; SPI = earned ÷ planned value; Cumulative CPI = earned value ÷ actual cost, including the overrun inherited at takeover; CPI since takeover counts only value earned and money spent from Nov 2, so it shows whether the overrun is still happening. Earned value = percent complete × budgeted hours × rate. Forecast at completion = spent so far + remaining work ÷ CPI since takeover. Site C has no hour estimates yet, so it is not priced.
| Project | Budget at completion | Planned value | Earned value | Actual cost | SPI | CPI | CPI since takeover | Forecast at completion |
|---|
Escalated items first, closed last. Weekly cost of delay is an illustrative assumption recorded with each item.
| Type | Project | Item | Status | Weekly cost | Decision |
|---|
This is a working lab by Manage Your Tech, run as a live program over several months. The plans are fictional and every figure is simulated or illustrative; no client data is used. Plans live in Microsoft Planner Premium, a scheduled Power Automate flow writes a weekly snapshot to Dataverse, and the risk register, rate card, baselines and actual costs are Dataverse tables.
Claude reads the data, drafts the weekly team updates, change requests and analysis, and builds these views. Every plan change, cost entry and decision is approved and applied by the PMO lead. This page is a frozen copy of the live Control Tower, refreshed at checkpoints.
Manage Your Tech · Governance Lab · Simulated data, snapshot refreshed at checkpoints · manageyourtech.ca